Re: Plan data transfer from PS to BCS

$
0
0

Hi Khadija,

The program  RFFMCY_CO_COPI is processes primary CO plan data from the COSP table for

the following activities:

 

Primary cost planning (RKP1)
Revenue element planning (RKP5)
Planning activity-dependent primary costs (RKP6)
Planning periodic reposting (RKPB)

 

The program processes secondary CO plan data in the COSS table for the following activities:

 

Planning settlement for internal activity allocation (KOAM)
Planning settlement (KOAP)
Planning debit from settlement (KOAS)
Planning periodical overheads (KZPP)
Planning activities (RKP2)
Planning secondary costs (RKP3)
Planning activity-dependent secondary costs (RKP7)
Planning settlement costs (RKP8)
Planning activity-dependent settlement costs (RKP9)
Planning indirect activity allocation (RKPL)
Planning overhead cost assessment (RKPU)
Planning overhead cost distribution (RKPV)
Secondary order cost planning (RKPW)
Activity-dependent secondary order cost planning (RKPX)
Planned credits for overheads (RKPZ)

 

It is not possible to extend it to activity KPPP.

Regards, Gordon