Hi SAP Experts,
Please could you advise?
We have experienced on a few occasions an issue with the Discontinuation Data in the BOM, specifically with the Item Line (structure POSNR) not being registered in MRP after the removal of the old pack material from the BOM, in a run-in out scenario. We have linkage with APO though the material in question is packaging that is planned through MRP.
After the old packaging item has been removed from the BOM, when production planning create a new plan the new packaging item fails to create demand and purchase requistions after the MRP run. Production Data has been re-dated to capture change via a change master number.
Could you please help how to resolve this issue, to get demand on new pack material and prevent a re-occurence when duplicate Item line numbers exist for follow-on effective out date materials.
Many thanks for your assistance
Regards
B.Rota