Hi gurus,
I hope someone can help.
I have a situation where I need to schedule raw materials to be delivered in hourly buckets, based on the requirements called for by the Production Schedule, due to storage space restrictions.
E.g.
- I have a silo that can hold 40 tonnes
- We could use anywhere from 20 tonnes/day - 150 tonnes/day
- I need to advise the supplier what times I need deliveries based on when the Production Schedule calls for the stock
- Bulk deliveries are made from the supplier of 20 tonnes a time
Is there a way for the system to create a Purchase Requisition with a timed delivery when the stock is needed, or is there a way to split the material requirements out into hourly buckets so that I can manually group the requirements into 20 tonne loads?
Thanks in advance