Goods receipt in Production Plant in Special procurement key 80

$
0
0

I have this scenario:

 

Planning    Plant A - Special procurement key 80

Production Plant B

 

1]After MRP Run its generated planned order for above material 

2] Production order created in Production plant B,

3] GR against production order updated stock in the planning plant A directly but I required that will be in production plant B.[as per SAP standard practice]

 

Because:

 

1. Transfer from Production Plant to Planning Plant required through STO process.

 

 

Please, your solution /work around for above process.

 

Thanks in advance