I have this scenario:
Planning Plant A - Special procurement key 80
Production Plant B
1]After MRP Run its generated planned order for above material
2] Production order created in Production plant B,
3] GR against production order updated stock in the planning plant A directly but I required that will be in production plant B.[as per SAP standard practice]
Because:
1. Transfer from Production Plant to Planning Plant required through STO process.
Please, your solution /work around for above process.